XV. Environmental Impact Assessment
Arkania argued customary international law required an environmental impact assessment given
the foreseeable risk of significant transboundary harm. Novaris disputed this, contending that the
environmental impact assessment jurisprudence developed around industrial projects and
identifiable transboundary resources cannot be automatically transposed onto novel atmospheric
consequences of re -entry. T he precise assessment cannot be demanded a s an accepted
methodology and amid preliminary science. Arkania maintained that the absence of established
methodology does not eliminate the underlying due -diligence obligation. Both parties agreed no
instrument in force between them in June 2032 expressly required such an assessment.