Supreme Court of India
Ch. Ramalinga Reddy v. Superintending Engineer and Anr.
INSC stands for INDIAN SUPREME COURT. A neutral citation scheme assigned by the Court itself, so a judgment can be cited without depending on a commercial law reporter. INSC is the neutral citation scheme assigned by the Supreme Court, so a judgment can be cited without depending on a commercial law reporter.
1 Supreme Court bench has cited this judgment.
What the Court ordered
In the result, the appeals are allowed only to this extent, that the appellant is entitled to receive, in respect of Claim lA, interest on the amount of the award for the period commencing on the date on which the arbitrator entered upon the reference and ending upon the date of the award, and the judgement of the High Court shall stan.d modified to that extent.
Judgment, page 11
From the headnote
Arbitration Act, 1940/Limitation Act, 1963: Sections 14, 30, 331 Article 119 (b)-Petition to challenge award-Starting point for /imitation Begins with service of notice of filing of award-Certain claims made by the Contractor .which were barred by contract between parties-Awarded by Arbitrator-Courts justified in interfering since Arbitrator has no jurisdiction to award such claims-Payment of interest for the period from the date the Arbitrator entered appearance till date of award-Held; Party entitled to interest for the said period Disputes having arisen in the execution of an excavation
Authorities it was built on
Where later benches applied it
Of those, 1 relied on
Sign in free to read it
- The full judgment, page by page, as published in the Supreme Court Reports
- The ratio: what the Court held, verbatim, with the page it sits on
- Every bench that relied on it, and every bench that argued against it
- Search every reported judgment, by party, citation or question
- Download the PDF, copy pinpoint citations ready for a filing
An email address, no password.